Bayou Rouge Permittee Responsible Mitigation (PRM) Site

  • Louisiana
  • St. Landry Parish
  • Vermilion-Teche Basin

RES worked diligently to deliver a custom turkey solution within 90 days for this schedule-driven pipeline. This Permittee’s project spanned 320 miles of 24-inch pipeline, originating in Donaldsonville, LA and terminating in Hastings, TX. RES worked closely with Denbury’s trusted consultants to assess impacts to wetlands and convert this data to an offset requirement. RES located and acquired land commensurate with the restoration preferences of the lead regulatory agency. Finally, RES developed a mitigation plan and obtained regulatory approval within the client’s accelerated timeframe. RES executes ongoing maintenance and monitoring for the client corresponding with its regulatory agreements.